The Worship Center, from Ground Breaking to Dedication!

In February of 2014 our Auditorium, which was built in 1953, collapsed due to snow load on the roof. This was a sad day for us but realizing that God’s plans are bigger than ours we began the process of envisioning what could be. We prayed and we planned. We celebrated God’s goodness and we raised the needed funds to begin our building project.

After spending 2 summer seasons in a Big Tent we finally broke ground in September of 2015 and we dedicated our new Worship Center on May 29, 2016! What a blessing it is to have this heated, air-conditioned, year around facility. This large, multi-purpose area is used for worship, concerts, retreats, conferences, weddings, and receptions. It has several smaller meeting rooms and a beautiful covered porch area for family and friends to gather.

Follow the building process via the photo galleries below!

September 6, 2015


September 8, 2015


September 9, 2015


As of Sept 30


October 7 – The walls are going up!


October 13 – pillars being set, walls getting higher!


October 21, 2015


October 27, 2015  – The walls are almost up, trenches are being dug and poles are going up for our 3 Phase Electric!


November 11, 2015 – The exterior wall are up and work has begun on the interior walls!  Soon the roof work will begin!


A lot of progress made in just one day!  Tuesday November,17,2015. The first picture was taken at 8:30 am, the last one at 4:00 pm


As of 11/23/15 – The progress continues!  We are thankful for the good weather we have had and for the safety of all of the construction crew!


December 2, 2015 – The roof is going on!


December 9, 2015 –  The progress continues!


December 16, 2015


As of January 13, 2016 – The cement floor has been poured!


As of January 28, 2016 –


February 16 – We have windows!


February 24, 2016 – a first look at the interior!


March 9, 2016


June 8, 2016: Presenting the New Worship Center!